Naples, Maine Causeway Construction Schedule Posted; Big Change Coming to Maine’s Sebago Lakes Region

Out and About for the Sebago Lakes Region of Maine, November 4 to 10
November 3, 2010
Out and About for the Greater Belgrade Lakes Region of Maine, Nov 11 to 17
November 10, 2010

Naples, Maine Causeway Construction Schedule Posted; Big Change Coming to Maine’s Sebago Lakes Region


The construction project that will eliminate the old swing bridge that connects the Naples, Maine Causeway between Long Lake and Brandy Pond and replace it with a permanent span has begun.
For years, the swing bridge has halted traffic while allowing watercraft of all shapes and sizes to pass between Long Lake and Brandy Pond. Now, a new bridge construction project has begun that will allow most boats and all vehicular traffic to proceed unabated in either direction, day and night, every day of the year.
While the debate over the bridge has, at times, been contentious, now that the project has finally been decided upon and begun, all eyes are on its progress and eventual completion and discussion is more focused on what the end result will be. Here is the proposed construction schedule as it has been recently published:
Award Project – Sept. 9, 2010
Mobilization – Sept. 2010 to Oct. 2010
Drainage on East Approach – Oct. 2010 to Jan.  2011
Drainage on Causeway – Oct. 2010 to Jan. 2011
Installing Sheet Piles on Causeway Bulkhead – Nov. 2010 to March 2011
Building Abutment #2 and Retaining Walls – Dec. 2010 to Nov. 2011
Backfilling Sheet Pile Wall – Jan. 2011 to April 2011
Constructing Docks – March 2011 to May 2011
Rebuilding Roadway, East Approach – April 2011 tp May 2011
Setting Curb, Building Sidewalks – May 2011 to August 2011
Installing Sheet Piles on Causeway Bulkhead – Nov. 2010 to March 2011 – June 2011 to July 2011
Backfilling Sheet Pile Wall – Jone 2011 to July 2011
Close Old Bridge to Boat Traffic – September 15, 2011
Building Abutment #1 and Ret. Walls – Oct. 2011 to Feb. 2012
Building Arch – Feb 2012 to May 2012
Construct and Pave Approaches – April 2012 to May 2012
OPEN NEW BRIDGE TO TWO WAY TRAFFIC – May 15, 2012
After the opening of the new bridge to two way traffic, construction and deconstruction will continue. The old swing bridge will be dismantled and boat traffic will commence by Memorial Day 2012. Paving will be completed throughout the summer of 2012 as well as plantings and landscaping, and general cleanup. The project will come to full completion on May 15, 2013.
For those of you travelling this route over the next two years, please be patient. We all hope the end result will be worth the wait, giving us better traffic flow for car and boat alike, while beautifying the Causeway overall.

Stay Informed

Get the latest lake news delivered direct from Maine’s lake expert, Tom Ferent